We installed a steel platform on the Dunn Building rooftop central utility plant for a new CenterPoint Energy transformer, along with over 2,000 feet of 5kV feeder under and through the existing facility up to Level Four. We also erected a new 1,500 SF steel frame electrical penthouse on the existing roof to house a 4,000A normal power substation and a 3,200A emergency power substation for future power needs. The penthouse was installed above a functioning operating room (OR).
To protect the operating room (OR) from water intrusion during construction, we created a sloped roof section, installed a sump pump for wind driven rain, and installed temporary roofing at the new building perimeter. We modified the steel structure to allow space for the largest piece of electrical gear and installed a removable roof access section into the new electrical room to install the electrical gear. Our efforts protected the OR while remaining on schedule.
1 million SF renovation of research buildings
1 million SF hospital renovations
Infrastructure upgrades
10,000 SF of electrical upgrades
25,000 SF of library infrastructure upgrades
145,000 SF landscape mall renovations and utility upgrades